Retainage

Also called: holdback, retention

Defined by the Research desk, The Lender Report · Sources reviewed

The share of each construction payment that is held back until the job is finished and the liens are cleared.

The word covers two layers. Under the construction contract, the owner holds back part of each payment to the contractor. Under the loan, the bank holds back part of each draw to the borrower.

On the loan side, the OCC handbook says that under a progress payment plan the bank normally retains, or holds back, 10 to 20 percent of each payment to cover cost overruns or unpaid bills from suppliers and subcontractors. The final draw usually pays out the holdback, after the bank confirms lien waivers or releases, reviews the final inspection report and sees the certificate of occupancy.

On federal construction contracts the rule is narrower. Retainage is used only when progress has not been satisfactory, and it may not exceed 10 percent.

Example: with a 10 percent holdback, a $400,000 draw request funds $360,000. The other $40,000 waits for the final draw, so someone has to carry it until then.

How it shows up in the data here

Retainage sits inside a single loan or contract, and no public file reports it. Bank call reports show only the construction and land balance held on the report date. To find lenders that carry construction loans, start at construction lenders or filter construction in search. The holdback percentage a given bank uses is not in any data here; it is set in the loan agreement.

Go further

Related terms

Sources

  1. OCC Comptroller's Handbook, Commercial Real Estate Lending, Version 2.0 (March 2022), page 49, retrieved .
  2. 48 CFR 32.103, Progress payments under construction contracts, retrieved .
  3. 48 CFR 52.232-5, Payments under Fixed-Price Construction Contracts, paragraph (e), retrieved .