The short answer
A construction loan package has five parts: a line-item budget with sources and uses, the plans and permits, the contractor and the contract, the sponsor's equity and guaranties, and the way out, which is a sale, a lease-up or a permanent loan. Banks expect the borrower's cash to go in first, fund the loan in draws against inspected work, and for commercial and multifamily construction work under a supervisory loan to value limit of 80 percent.
What the lender is deciding
Four questions, in this order. Will the project get built for the budget? Will it be worth more than the loan when it is done? How does the loan get repaid? And if something goes wrong, who has the money and the skill to finish?
Lenders hold $470B FDIC call reports and NCUA 5300, in construction and land loans. The 2006 interagency guidance gives these loans a supervisory screen of their own, at 100 percent of a bank’s total capital, so a bank’s room for them can move from year to year. See the concentration guide.
Part 1: budget, sources and uses
- A line-item budget: land, hard costs by trade, soft costs, financing costs, contingency
- Sources and uses on one page
- The land purchase contract or closing statement, and what has been spent to date with proof
- An interest reserve calculation showing how interest is paid during construction and lease-up
- A contingency line, stated as a share of hard costs
- A cash flow schedule by month: draws, equity, interest
Land you already own counts as equity at a value the lender accepts, which is often what you paid plus documented improvements, not today’s appraisal. Ask how the lender will count it.
Part 2: plans, permits and feasibility
- Plans and specifications, as complete as they are
- Zoning confirmation and the status of every approval and permit
- A survey and a geotechnical report, if done
- Environmental reports on the site
- A market study or your own evidence of demand: comparable rents or sales, absorption, competing projects
- A pro forma: stabilized income and expenses for a rental project, or a sales schedule for a for-sale project
- Pre-leasing or pre-sales: signed leases, letters of intent, or contracts
Part 3: the contractor and the contract
- The construction contract. Lenders prefer a fixed price or a GMP contract over cost-plus with no ceiling
- The general contractor’s license, references, financial statement and list of completed projects of this kind
- The schedule, with milestones
- Insurance certificates: builder’s risk, liability, workers’ compensation
- Payment and performance bonds, if the lender requires them
- The architect’s and engineer’s contracts
- The retainage terms
If the sponsor is also the builder, say so plainly. The lender will look harder at the budget and may want a third-party cost review.
Part 4: sponsor, equity and guaranties
- Financial statements, tax returns and a schedule of real estate owned for each guarantor
- Proof of the cash equity, in account statements
- A record of projects built: type, size, cost, outcome
- Contingent liabilities, including guaranties on other construction loans
- Entity documents and an ownership chart
Expect three guaranties to be discussed. A repayment guaranty covers the loan. A completion guaranty is a promise to finish the building and pay cost overruns. A carry guaranty covers interest and operating shortfalls until the project is stable. Which the lender asks for, and whether any falls away later, is negotiated. See guarantor strength and recourse.
Part 5: the way out
A construction loan is temporary. The lender wants to see how it ends.
- Sale. For-sale projects repay from closings. The lender sets a release price for each unit.
- Permanent loan. A rental project is refinanced once it is leased. A take-out commitment from a permanent lender, or evidence that the finished project fits a known program, makes this concrete.
- Conversion. Some banks write a construction loan that converts to a mini-perm term loan at completion.
Show the permanent loan the finished project would support, using the same coverage and loan to value tests a permanent lender would. If that loan is smaller than the construction loan, the gap is the lender’s first question.
Looking for a lender now? Find lenders for this in your state or see Construction lenders state by state.
How the money moves
Equity first. Most lenders require the borrower’s cash to be spent before the first loan dollar. The capital rule’s treatment of high volatility commercial real estate gives banks a regulatory reason as well. See the supervisory loan to value and HVCRE guide.
Draws. The loan is advanced in draws, usually monthly, against work in place. NCUA’s rule for credit unions spells out a process that banks follow in much the same form by policy: a line-item budget reviewed before closing, a requisition and disbursement process, release of funds “only after on-site inspections, documented in a written report by qualified personnel,” confirmation that the remaining funds are “sufficient to complete the project,” and confirmation with each draw “that no intervening liens have been filed.”
In balance. At every draw the money left in the loan plus remaining equity must cover the cost to finish. If the budget grows, the borrower funds the difference before the next draw.
The limits behind the lender’s answer
Supervisory loan to value limits for bank real estate loans (12 CFR part 365, appendix A)
| Loan category | Limit |
|---|---|
| Raw land | 65 percent |
| Land development | 75 percent |
| Construction: commercial, multifamily and other nonresidential | 80 percent |
| Construction: 1- to 4-family residential | 85 percent |
| Improved property | 85 percent |
These are ceilings for a bank’s own policy, measured against the value of the finished project. They are not what a bank will lend. For credit unions, 12 CFR 723.6 sets collateral value for a construction loan as “the lesser of the project’s cost to complete or its prospective market value.”
Worked example (hypothetical). A 40-unit apartment project will cost $10,000,000: $1,500,000 for land, $7,200,000 of hard costs, $900,000 of soft costs and $400,000 of interest reserve. The appraiser’s value when complete and stabilized is $12,500,000.
Value test. Say the bank’s policy limit is 70 percent of completed value. 70 percent of $12,500,000 is $8,750,000. The supervisory ceiling of 80 percent would be $10,000,000, which is the whole cost. A bank’s own limit sits below the ceiling.
Cost test. Say the bank also limits the loan to 75 percent of cost. 75 percent of $10,000,000 is $7,500,000.
The loan. The smaller figure, $7,500,000. Equity is $2,500,000. If the land is owned free and clear and the bank counts it at its $1,500,000 cost, the sponsor needs $1,000,000 more in cash, spent before the first draw.
Way out. If stabilized net operating income is $800,000 and a permanent lender tests coverage at 1.25 on a 6.5 percent, 30-year loan, each $1,000,000 costs about $75,800 a year, so $640,000 of payment supports about $8,440,000. That is above $7,500,000, so the takeout covers the construction loan with room.
The 70 percent, 75 percent, 1.25 and 6.5 percent are this example’s assumptions.
Finding construction lenders
The public record is thin. Banks report the balance of construction and land loans they hold, in call report item 1.a, split into 1-4 family residential construction and everything else. Credit unions report construction and development loans held and made this year. No public file lists individual construction loans, because Regulation C excludes temporary financing.
So search on the balance, the change over a year, capital and branches. Unused commitments on a bank’s page show construction money promised and not yet drawn. Then call, because appetite for construction can change from one quarter to the next.
Want a person to check the public record for a commercial construction loan? Request financing from The Lender Report’s operator. A person replies by email, usually naming lenders that have made loans like yours. It is free, it covers business and investment property loans only, and nothing is sent to a lender.
What the public record can and cannot tell you
It can: show which lenders hold construction loans, how the balance has moved, and which are large enough for the loan.
It cannot: show property types, loan to cost limits, pricing, whether a lender is adding construction loans now, or any single loan.
Questions to put to the lender
- Are you adding construction loans this year, for this property type?
- What are your limits on loan to cost and loan to completed value?
- How do you count land I already own?
- Which guaranties do you require, and does any fall away at completion or stabilization?
- How do draws work: who inspects, how long from request to funding, what is retained?
- Does the loan convert to a term loan, and on what test?
Terms used here
- Construction loan: A short-term loan that pays for building or renovating a property, advanced in stages as work is finished and repaid from a sale or a permanent loan.
- Construction draw: One advance of construction loan money, released after the lender confirms that the work it pays for is in place.
- Retainage: The share of each construction payment that is held back until the job is finished and the liens are cleared.
- Interest reserve: An account set up by the lender that pays the loan's interest during construction and lease-up, usually funded as a line in the loan budget.
- Completion guaranty: A guarantor's promise to the lender that a project will be finished and its bills paid, without a promise to repay the whole loan.
- Cost overrun: The amount by which a construction project costs more than its budget, which the borrower is normally expected to cover.
- Payment and performance bond: Two surety bonds on a construction contract: one backs payment of subcontractors and suppliers, the other backs completion of the work.
- As-complete value: An appraiser's estimate of what a property will be worth on the date construction is expected to be finished.
- Loan-to-cost ratio (LTC): The loan amount divided by the total cost of a project: the property plus all construction costs. It shows how much of the budget the lender funds.
- Loan-to-value ratio (LTV): The loan amount divided by the value of the property securing it. A $700,000 loan on a property valued at $1,000,000 is 70 percent loan to value.
- Take-out loan: The permanent loan that pays off a construction loan, or the commitment from a lender to make that loan once the project is finished and leased.
- Mini-perm: A medium-term loan, shorter than a permanent loan, that a bank makes on a finished property so the owner has time to lease it up before long-term financing.
- Permanent loan: A longer-term loan on a finished, leased property that replaces the construction or bridge loan and is repaid from the property's income.
- HVCRE exposure: A land, development or construction loan that a bank must carry at a 150 percent risk weight under the capital rule unless the project meets an exemption, such as 15 percent borrower capital.
- ADC loan: A loan to acquire land, develop it or build on it, repaid from the sale, lease-up or refinance of the finished project. Banks report these as construction, land development and other land loans.
Sources
Every rule and outside figure above comes from one of these, opened on . Dates are the source's own. Figures from this site's data carry their own source and date beside them.
- 12 CFR part 365, appendix A, Interagency Guidelines for Real Estate Lending Policies (supervisory loan-to-value limits), retrieved .
- 12 CFR 723.6, Construction and development loans (NCUA), retrieved .
- FFIEC 051 instructions, Schedule RC-C, item 1.a, construction, land development, and other land loans (hosted by the FDIC), dated .
- 12 CFR 1003.3, Regulation C: temporary financing is excluded, retrieved .
Next step: check the record
- Lenders for constructionBanks and credit unions by construction and land loans held, from their own filings.
- Loan Comps for a construction loanLenders that hold construction loans in a state and are large enough for this amount.
- Loan to value and loan to costWork out both ratios and the equity each one implies.
Keep reading
- LTV and LTC calculator: Loan to value and loan to cost, the equity a lender will ask for, and the federal supervisory limit for the property type.
- Maximum loan calculator: The loan each test allows: DSCR, LTV and debt yield side by side, and which one binds.
- Deal summary builder: Turn the facts of a deal into a clean one-page summary you can copy or print. Nothing is saved or sent.
- Supervisory loan to value limits and HVCRE, explained: Two federal rules shape how much a bank will lend against real estate: a table of loan to value ceilings, and a capital rule that makes some construction loans cost the bank more to hold.
- Residential development loan package checklist: Lots and houses are repaid one sale at a time. A lender on a subdivision or a group of homes is underwriting how fast those sales will come and what happens to the loan if they slow down.
- The CRE concentration guidance, explained: Bank regulators watch how much commercial real estate a bank holds against its capital. The guidance sets two screens. It does not set a limit, and it does not count owner-occupied buildings.
- Guarantor strength and recourse, explained: A guaranty is the lender's second way out. Whether you sign one, how much it covers and what the lender checks before accepting it shape a commercial loan as much as the rate does.
- How bankers evaluate a commercial loan deal: A credit officer asks one question five ways: how will this loan be repaid, and what happens if it is not? Knowing the five tests lets you size a request before you send it.
- Multifamily loan checklist for 5+ unit properties: A larger apartment loan can go to five kinds of lender. They want much the same package. They differ on recourse, term, prepayment, speed and what they ask of the sponsor.
- What a lender-ready loan package looks like: A lender decides in minutes whether to keep reading. A package that answers the first five questions on one page, and backs each answer with a document, gets read.
Questions people ask
How much cash does a construction borrower need?
Each lender sets its own requirement. The interagency guidelines set a supervisory loan to value limit of 80 percent for commercial, multifamily and other nonresidential construction, measured against the value when complete, and a bank's policy limit is usually lower. Most lenders also cap the loan as a share of cost.
Is there a public list of construction loans by lender?
No. Banks report only the total balance of construction and land loans they hold. HMDA excludes temporary financing, which covers most construction loans. Credit unions report construction loans made during the year as a total.
What is retainage?
A share of each payment to the contractor that is held back until the work is finished. The construction contract sets the percentage, and the lender's draw process follows it.
Cite this
Source: The Lender Report, Construction loan package checklist, https://lender.report/guides/package-checklist-construction/, data as of November 11, 2026.
General information, not legal, tax or credit advice. A lender's own policy decides what it will do; ask it for the policy in writing.
Source and date appear beside each figure. Banks report balances, not loans made. Loans made come only from HMDA and SBA files. We do not audit filings and can make errors joining them. Report a problem